This Note discusses the conditions under which the contract price may be increased and the time to perform obligations may be extended under a lump sum engineering, procurement, and construction contract.

EPC Contract Drafting Considerations: Increased Costs and Extensions of Time

Practical Law Practice Note 0-560-5589 (Approx. 9 pages)

EPC Contract Drafting Considerations: Increased Costs and Extensions of Time

by Practical Law Finance with Sarah Biser, Fox Rothschild LLP and Robert Rubin, McCarter & English LLP
MaintainedUSA (National/Federal)
This Note discusses the conditions under which the contract price may be increased and the time to perform obligations may be extended under a lump sum engineering, procurement, and construction contract.