Interplay between section 9 and section 44 Arbitration Act 1996 (TCC) | Practical Law

Interplay between section 9 and section 44 Arbitration Act 1996 (TCC) | Practical Law

In Jacobs E&C Limited v Laker Vent Engineering Ltd (2015), the court considered an application for an interim mandatory injunction and a cross application for a stay of the court proceedings.

Interplay between section 9 and section 44 Arbitration Act 1996 (TCC)

Practical Law UK Legal Update Case Report 5-615-7445 (Approx. 5 pages)

Interplay between section 9 and section 44 Arbitration Act 1996 (TCC)

Published on 03 Jun 2015England, Wales
In Jacobs E&C Limited v Laker Vent Engineering Ltd (2015), the court considered an application for an interim mandatory injunction and a cross application for a stay of the court proceedings.