Payments suspended by section 2(a)(iii) of ISDA® Master Agreement included for netting purposes (High Court) | Practical Law

Payments suspended by section 2(a)(iii) of ISDA® Master Agreement included for netting purposes (High Court) | Practical Law

In Pioneer Freight Futures Company Ltd v TMT Asia Ltd [2011] EWHC 1888 (Comm), the High Court has held that payment obligations that are suspended under section 2(a)(iii) of the 1992 ISDA Master Agreement should be taken into account for netting purposes under section 2(c).

Payments suspended by section 2(a)(iii) of ISDA® Master Agreement included for netting purposes (High Court)

by PLC Finance
Published on 01 Sep 2011England, Wales
In Pioneer Freight Futures Company Ltd v TMT Asia Ltd [2011] EWHC 1888 (Comm), the High Court has held that payment obligations that are suspended under section 2(a)(iii) of the 1992 ISDA Master Agreement should be taken into account for netting purposes under section 2(c).