Clause stipulating arbitration by SIAC under ICC Rules upheld as valid | Practical Law

Clause stipulating arbitration by SIAC under ICC Rules upheld as valid | Practical Law

Alvin Yeo, Senior Counsel (Senior Partner) and Andre Maniam (Head of Litigation & Dispute Resolution Department), WongPartnership LLP

Clause stipulating arbitration by SIAC under ICC Rules upheld as valid

Practical Law UK Legal Update Case Report 7-386-3308 (Approx. 4 pages)

Clause stipulating arbitration by SIAC under ICC Rules upheld as valid

Published on 01 Jul 2009Singapore
Alvin Yeo, Senior Counsel (Senior Partner) and Andre Maniam (Head of Litigation & Dispute Resolution Department), WongPartnership LLP
The validity of a "hybrid" arbitration clause (that is, a clause providing that an arbitration is to be carried out before one arbitral institution but using the rules of another arbitral institution) was recently considered by the Singapore Court of Appeal in Insigma Technology Co Ltd v Alstom Technology Ltd [2009] SGCA 24. The appellant, Insigma Technology Co Ltd (appellant), had sought to challenge the validity of such an arbitration clause. The clause was upheld by the High Court, and on appeal, was also upheld by the Court of Appeal.

Facts

The appellant entered into a licensing agreement with Alstom Technology Ltd (the respondent). This agreement, among other things, provided for arbitration in the event of a dispute between the parties. The arbitration clause stated:
"Any and all such disputes shall be finally resolved by arbitration before the Singapore International Arbitration Centre in accordance with the Rules of Arbitration of the International Chamber of Commerce then in effect and the proceedings shall take place in Singapore and the official language shall be English…"
An arbitration was duly commenced when a dispute arose between the parties. The proceedings were initially commenced at the International Chamber of Commerce (ICC) by the respondent. However, the appellant objected to the commencement of the arbitration at the ICC on the basis that the arbitration clause provided that the dispute be resolved by arbitration before the Singapore International Arbitration Centre (SIAC) not the ICC.
At that stage, the appellant suggested that the SIAC could administer the arbitration under the rules of the ICC (ICC Rules). The respondent therefore enquired with the SIAC whether it would be able to administer such an arbitration. The SIAC replied in the affirmative: it agreed to administer the arbitration pursuant to the ICC Rules, and confirmed that it had departments/officers that could fill roles equivalent to those provided by the ICC and stipulated in the ICC Rules. The ICC proceedings were therefore withdrawn and proceedings were recommenced under the administration of the SIAC, which proceeded to appoint arbitrators to constitute an arbitration tribunal.
After the arbitration tribunal was constituted, the appellant challenged the validity of the arbitration clause, contending that it was void for uncertainty. It also challenged the tribunal's jurisdiction to hear the dispute on the basis that the ICC Rules required the tribunal to be constituted by the ICC and not the SIAC.
These preliminary challenges were considered by the tribunal and rejected. The appellant then appealed to the Singapore High Court and raised the same issues. The High Court too dismissed the appeal. The appellant then commenced a further appeal to the Court of Appeal where the same issues were raised.

Decision

The arbitration clause was held to be valid. It was construed as providing for an arbitration to be administered by the SIAC applying the ICC Rules. The approach adopted by the court in considering the arbitration clause is instructive as it clearly upholds party autonomy and their freedom to contract. The court also agreed with the High Court that there was nothing to prevent parties from agreeing that one institution should conduct the arbitration in accordance with another institution's rules.
The court made the following useful observations in its judgment on the approach to be taken in relation to such arbitration clauses:
  • It would seek to give effect to the parties' clear intention to settle their disputes by arbitration, even if certain aspects of the agreement to arbitrate might be ambiguous, inconsistent, incomplete or lacking in certain particulars. This approach was subject to the following qualifications:
    • The arbitration could be carried out without prejudice to the rights of either party; and
    • It did not result in an arbitration that had not been in the contemplation of the parties.
  • That when construing an arbitration clause, courts adopt a commercially sensible and logical construction rather than one that is commercially illogical.
  • Public policy was in favour of upholding such clauses in accordance with the parties’ intentions and in upholding party autonomy.
The court held that the arbitration clause was not void for uncertainty. While the ICC rules are drafted to provide for certain specific officers/departments in the ICC to carry out certain specific functions, the court noted that the roles carried out by these officers/departments could, within the context of the arbitration, be carried out by equivalent officers/departments in the SIAC. Furthermore, this had in fact been confirmed by the SIAC to the parties prior to commencement of proceedings. As noted by the High Court, the arbitration clause would only be unworkable if such equivalent officers/departments had not been available. This, however, was not the case here.

Comment

This decision reaffirms the pro-arbitration approach of the Singapore courts and provides assurance that they will, in construing arbitration agreements, seek to uphold the intention of the parties to arbitrate. The case does, however, highlight the need to be cautious when agreeing to such a "hybrid" arbitration clause.
In this case, the appellant's apparent lack of good faith in objecting to an interpretation of the clause which it had, prior to that, adopted; and the fact that the SIAC had been willing to administer the arbitration under the ICC rules with its own departments/officers acting in roles equivalent to those stipulated in the ICC rules, possibly militated against the court finding the clause void for uncertainty. Further, both the Court of Appeal and the High Court had made clear their view that the clause would have been unworkable if the SIAC had been unable to provide similarly equipped substitute bodies.